Atyrau Refinery Reconstruction Project

PROJECT DETAILS

TEKFEN JOB NO: 358

LOCATION: Tengiz, Atyrau, Kazakhstan

CLIENT: TengizChevroil LLP (TCO)

CONTRACTOR: GATE Construction

COMMENCEMENT: 15/05/2017

COMPLETION: Ongoing

Project Description:

Construction of additional units (gasoline, diesel, sulfur, hydrogen, coker) and renovation works for the Atyrau Refinery.

Civil construction works:

  • Structural Concrete: 7.000 m3
  • Paving Area: 21.000 m2
  • Buildings: 1.195 m2
  • Floor Heating Area: 1.500 m2

Structural steel works:

  • Fabrication and erection: 1.700 ton
  • Cladding (Roofing & Siding): 7.000 m2

Mechanical works:

  • Equipment erection: 2.800 ton (Drum, Reactor, Vessel, Tank, Exchangers, Air Fin Coolers)
  • Furnace: 5 set
  • Rotary Equipments: 113 set (Pumps, Compressor, Blower & Fan)

Piping:

  • Prefabrication and Field Welding: 292.000 ID
  • Post Weld Heat Treatment and Radiographic Inspection

Electric and instrumentation works:

  • Local Instrument & Panel Installation: 986 set
  • Conduit Pipe Installation: 16.658 m
  • Instrumentation cable: 150.000 m
  • Power and Control Cable: 243.000 m
  • Insulation, painting and fire proofing;
  • Equipment Insulation: 5.000 m2
  • Piping Insulation:160.000 I.M.
  • Painting: 97.500 m2
  • Pipe Wrapping: 1.000 m2
  • Fire Proofing by concreting: 1.270 m2