TEKFEN JOB NO: 361
LOCATION: Tengiz, Atyrau, Kazakhstan
CLIENT: TengizChevroil LLP
CONTRACTOR: GATE Construction
COMMENCEMENT: 01/12/2017
COMPLETION: 24/04/2022
FGP Multi Well Pad Project is between TCO (TengizChevroil) and GATE (Tekfen 100%), start date is 24.11.2017 and the construction works start date is 30.03.2018 in Tengiz Region and the project period is 53 months. The estimated completion date of the project according to the contract is 24.04.2022.
Company is planning a major expansion of capacity at its existing Facilities at Tengiz and Korolev oilfields in Western Kazakhstan through the development of the Future Growth Project (WPMP). Construction and commissioning for Third Generation Production Area 51 MWP civil, mechanical, electrical and instrumentation works and describes the obligations of Company and Contractor during performance of the work.
Item | Quantity | Unit |
---|---|---|
Backfill (1Bt) | 622,650 | M3 |
Backfill (6Ft) | 213,418 | M3 |
Fencing | 16,565 | M |
Piling | 4,325 | EA |
Structural Concrete | 29,681 | M3 |
Wire and Cable | 1,210,808 | M |
Grounding and Lightning Protection | 107,385 | M |
Termination | 28,779 | EA |
Electrical Heat Tracing | 39,631 | M |
Misc Electrical Device | 3,748 | EA |
Fire & Gas Instruments | 5,734 | EA |
Primary Cable Tray and Accessories | 43,205 | M |
Module Electrical Equipment | 19 | EA |
Insulation | 32,615 | M |
Processing Equip, Flares, Other | 124 | EA |
Painting | 36,709 | M |
Shop Pipe Fabrication | 36,760 | M |
Aboveground Piping | 38,875 | M |
Piperacks, Equipment Structures | 2,421,795 | KG |