2x35 MW Kashagan Natural Gaz Fired Simple Cycle Power Plant

PROJECT DETAILS

TEKFEN JOB NO: 350

LOCATION: Tengiz, Atyrau, Kazakhstan

CLIENT: TengizChevroil LLP (TCO)

CONTRACTOR: GATE Construction

COMMENCEMENT: 15/08/2016

COMPLETION: 29/08/2019

Project Description:

Execution of all civil works, steel structure, mechanical, electrical erection, piping, instrumentation, painting and insulation works of 238 MW natural gas fired combined cycle power plant composed of 4x42 MW gas turbines and 2x35 MW steam turbines for the power supply for Trench 1 and 2 of Kashagan Petroleum Area.

Civil works

  • Backfill: 40.000 m3
  • Concreting: 9.000 m3
  • Roads: 12.250 m2

Structural steel erection

  • 2.900 ton

Equipment erection

  • Gas Turbines: 340 ton
  • Gas Turbine Generators: 288 ton
  • Gas Turbine Gearboxes: 80 ton
  • Steam Turbines: 194 ton
  • Steam Turbine Generators: 150 ton
  • Air coolers: 170 ton
  • Overhead Cranes: 45 ton
  • Stacks: 185 ton
  • Balance of Plant: 1.000 ton
  • Total: 2.500 ton

Piping

  • Pipe and Fittings: 600 ton
  • Pipe Supports: 40 ton

Electrical erection

  • Cabling: 216.000 m
  • Cable Trays: 52.000 m
  • Power Transformers: 23 each
  • Switchyard, Transformer Station, Control Center

Instrumentation

  • 1.500 each instrument installation
  • SS Tubing: 2.000 m